Open Access Articles- Top Results for Namma Metro

Namma Metro

Namma Metro
150px
290px
Overview
Native name ನಮ್ಮ ಮೆಟ್ರೋ
Owner Bangalore Metro Rail Corporation Limited (BMRCL)
Locale Bangalore, Karnataka, India
Transit type Rapid transit
Number of lines 2 (operational)
2 (Phase I Target-Mar 2016)
4 (Phase II Target-Dec 2019)
Number of stations 16 (operational)
41 (Phase I Target-Mar 2016)[1]
102 (Phase II Target-Dec 2019)[2]
Daily ridership 40,380 (March 2014)[3]
Chief executive Pradeep Singh Kharola, MD
Headquarters BMTC Complex, Shanthinagar, Bangalore
Website bmrc.co.in
Operation
Began operation 20 October 2011 (2011-10-20)
Operator(s) Bangalore Metro Rail Corporation Ltd. (BMRCL)
Train length 3 coaches
Headway 10–15 minutes
Technical
System length Script error: No such module "convert". (Phase I)[1]
Script error: No such module "convert". (Phase II)
No. of tracks 2
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Electrification 750V DC Third rail
Average speed Script error: No such module "convert".
Top speed Script error: No such module "convert".

Namma Metro (literally "Our Metro") also known as Bangalore Metro, is a metro system for the city of Bangalore, Karnataka, India. The agency responsible for its implementation is the Bangalore Metro Rail Corporation Ltd (BMRCL), a joint venture of the Government of India and the Government of Karnataka.[4] The first stretch (Reach 1) between Baiyyappanahalli and M.G. Road was inaugurated on 20 October 2011.[5] Reach 3 & 3A between Sampige Road and Peenya Industrial Area was inaugurated on 1 March 2014.[6]

Background and planning

Background

A number of studies aimed at providing an efficient public transport system for Bangalore have been conducted, the oldest being the study carried out by the Central Road Research Institute in 1963. Although the study proposed a 26 km rail network, it generally concentrated on the road network and traffic management system. In 1982, based on data collected between 1977 and 1979 a study group nominated by the Government of Karnataka gave a report for improvement of the transport system in the city. The study recommended a metro system, but like the previous study, concentrated on road improvements and provision of grade separators. In 1983, the Metropolitan Transport Project, a team of the Southern Railway prepared a feasibility report for introducing suburban services on existing lines, a ring railway and a rapid rail transit system on two corridors. The total cost of the project at 1983 prices was Rs. 650 crores. However, the report was not followed up.[7] In 1988, a World Bank aided study and part of the Bangalore Urban Transport Project was carried out by RITES. The recommendations were for improvement of road transport system, though the provision of suburban services on the existing rail network was also recommended. The first Mass Rapid Transport System (MRTS) for Bangalore was proposed in January 1993, based on the 1983 report, by an Official Committee nominated by the State Government. The work was to be carried out in two phases. The first phase would have involved the construction of a partly underground 12.9 km MRTS line from Rajajinagar to Jayanagar, and a suburban corridor on the existing rail network. The second phase would have involved the construction of a 11.2 km MRTS line from Hudson Circle to Krishnarajapuram, and a 57.9 km circular railway.[7]

In 1994, the State Government incorporated a company named the Bangalore Mass Rapid Transit Limited (BMRTL) under the Companies Act, 1956 to implement the MRTS. BMRTL in turn asked IL&FS to carry out a feasibility study for a rapid transit system on public-private partnership basis.[7][8] The main recommendations of the study were:

  • An elevated LRT system on 6 routes - Yeshwantapur to Kanakpura via Rajaji Nagar and Jayanagar, Hudson junction to Indira Nagar via M G Road and Airport, Yeshwantapur to Mayo Hall via Mekhri junction, Jayanagar to Mayo Hall via Koramangala, Chord road to Kanakpura via Banashankari, and Ulsoor to Mekhri Circle and Hebbal.
  • Legal cover under the Tramways Act.
  • The traffic forecast were made for the year 2001 and 2011.
  • Recommended a fare of Rs. 0.55 per pkm (1994 prices). Indicative fares in July’2000 was Rs. 2.25 per Km.
  • Capacity of the system as 24850 phpdt.
  • Train headway varying from 5.45 mts to 30 mts on various sections.
  • Special rolling stock with 750 volt dc traction system.
  • Total construction period 7.5 years from 1 April 1999.
  • Total cost of the project as Rs. 2025 crores (excluding land) at 1994 prices. Indicative cost in July’2000 was Rs. 80 to Rs. 100 Crores per route km.
  • IRR projected as 12.9% (upto 2030).[7]

However the project could not take off for various reasons, despite fixing a private partner for implementation of the project. While the implementation of the LRT project was delayed due to various reasons, the worsening traffic in Bangalore led to the State Government asked the DMRC to step in and propose a metro system on two busy corridors for implementation as a fast track project more or less on similar lines as the Delhi Metro.

Planning

During August - October 2002 the Karnataka Government began discussions with the Delhi Metro Rail Corporation (DMRC) for preparation of a detailed project report (DPR) for a metro system for Bangalore. The successful planning and implementation of the Delhi Metro project by the DMRC encouraged the State Government to avail their expertise for the planning, investigation and preparation of a DPR for two metro lines in Bangalore - one in the east-west direction and the other in the north-south direction. The Karnataka Government vide their D.O. letter No. UDD 144 PRJ 2002 dated 19 September 2002 conveyed their consent to DMRC to take up the DPR work and based on the instructions conveyed in this letter, the Bangalore Mass Rapid Transit System Ltd. (BMRTL) placed an order on DMRC vide letter No.BMRTL/DMRC/02/372 dated 31 October 2002 for the same for taking up the assignment.[7]

DMRC began work on the DPR in October 2002, and took up the field studies and identified the two corridors which were then cleared in principle by Karnataka Government vide their letter No.UDD 144 PRJ 2002 dated 19 September 2002 and No.UDD 144 PRJ 2002 dated 19 October 2002 respectively. DMRC carried out the topographical and traffic surveys with the assistance of RITES who also assisted them in drawing up the DPR. The detailed geo-technical studies were got done through Torsteel Research Foundation in India, Bangalore (TRFI). For the environmental studies the services of the Department of Environmental Sciences of Bangalore University were availed. For carrying out the fare structure study and for arriving at the fares to be levied, the services of the National Council of Applied Economic Research (NCAER), Delhi were taken. DMRC availed the assistance of ICICI in regard to financing the project and for arriving at the financial analysis. During the preparation of the DPR there were constant interactions between the DMRC and the Karnataka Government and various State Governmental and municipal agencies. The DMRC was also assisted by the BMRTL, who had made available some of their previous studies and relevant information needed for preparing the DPR.[7] DMRC, after numerous site visits, detailed reconnaissance and study of past reports including the traffic pattern recommended two corridors - an east-west corridor and a north-south corridor - which would become the first phase of the project.[7]

The east-west corridor would begin at Baiyappanahalli and traverse through Indiranagar, CMH Road, Swamy Vivekanand Road, M G Road, Ambedkar Road, Post Office Road, K G Road, Majestic, KSRTC bus stand, Bangalore city Railway station, Magadi Road, Toll Gate junction, Chord road, Vijay Nagar and Mysore road and terminate at the Ring Road junction. The north-south corridor would begin from Yeshwantapur in the north and pass through Chord Road, Mahakavi Kuvempu Road, Swastik, Platform Road, KSRTC bus stand, Chickpete, City Market, K R road, Vanivilas Road, Lal Bagh, Southend circle and R V road and terminate at J P Nagar. The two lines cross each other at Majestic, close to the City Railway station, where a rake interchange line connecting the two corridors was also proposed. These corridors mostly cover the two priority corridors of the earlier LRT system but with provision of underground sections in the Central Business District (CBD) area which were avoided in the LRT corridors. Thus the recommended corridors were shorter in length than the LRT corridors. The two proposed lines would serve the most congested area of the city (the CBD), without which the DMRC felt that the system may not succeed. The DMRC also justified the selection of the corridors by the traffic demand forecast. The selected corridors were approved in principle by the State Government before detailed surveys were undertaken.[7]

The DMRC submitted the DPR for Phase I of the Namma Metro project to the BMRCL in May 2003. The final approval on a scheme that incorporated the expertise of DMRC and RITES Limited did not come until April 2006.[9] The DPR prepared by DMRC envisaged a Script error: No such module "convert". elevated and underground rail network with 32 stations for Phase I of the project. The proposed gauge was standard gauge unlike the broad gauge on the Delhi Metro network. The rationale for the metro includes reduced journey times, cutting fuel use, accident reduction and lower pollution.[citation needed]

Construction

Phase I

File:Namma Metro Phase 1 line map.png
Map of Phase I of the Namma Metro.

Phase I spans a length of 42.3 km and consists of 2 lines:[10] Implementation of Phase I has been divided into 4 "reaches" and 2 underground sections. It will be fully opened for service from March 2016. As Chief Minister Siddaramaiah informed the Legislative Assembly in January 2014, the total project cost is expected to be 138.45 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). billion) due to cost escalation following unexpected delays in meeting the deadlines. The delays result in a cost escalation of 34.73 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million).

Line[11] Elevated length (km) Underground length (km) Total length (km) % of length on curves Stations
Purple Line 13.22 4.88 18.10 44.30 % 17
Green Line 20.20 4 24.20 39.70 % 24
Total 33.42 8.88 42.30 - 41
Rake interchange line 0 0.35 0.35 100% 0

The schedule for completion of Phase I is as follows:[12]

Section Termini Opening date
Reach 1 (east) Baiyyappanahalli M.G. Road 20 October 2011
Reach 2 (west) Mysore Road Magadi Road June 2015[13]
Underground UG2 (east to west) M.G. Road Magadi Road November 2015[14]
Reach 3 (north) Sampige Road Yeswanthpur 1 March 2014
Reach 3A (north) Yeswanthpur Peenya Industry 1 March 2014
Reach 3B (north) Peenya Industry Nagasandra 1 May 2015[15]
Underground UG1 (north to south) Sampige Road National College March 2016[16]
Reach 4 (south) National College R.V. Road March 2015
Reach 4A (south) R.V. Road Puttenahalli March 2015

Construction work for Phase I of the project was scheduled to start in 2005 but was delayed by a February 2006 change of government in Karnataka and continued debate over whether the project was financially feasible and appropriate for the city. Finally, on 25 April 2006 the Indian Cabinet approved the project, which was then budgeted at more than 54 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million) (Later revised to 116.09 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). billion) for Phase I).[17] In 2006, Navayuga Engineering was awarded the contract to construct Reach 1 of the East-West corridor.[18] The foundation stone for the Phase I construction was laid by Prime Minister Manmohan Singh on 24 June 2006,[19] and civil construction on Reach I of the line, between M.G. Road and Baiyyappanahalli, commenced on 15 April 2007.[20][21] In 2007, BMRCL announced that it would incorporate a northern extension (from Yeshwanthapura to Hesaraghatta Cross) and part of the southern extension (from RV Road to Puttenahalli) in Phase I, thus extending the length of Phase I network to about Script error: No such module "convert"., with 40 stations. The objective was to connect the metro to the Outer Ring Road at both ends, and also cover the industrial areas of Peenya in the north-west, thereby providing better connectivity and increasing ridership.[citation needed] In October 2008, the Government of Karnataka approved this extension, which would cost an additional 15.92 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million).[22]

The underground work of Phase I commenced in May 2011. Each corridor consists of two tunnels which are the first underground tunnels built for trains in South India. The tunnels, dug using tunnel boring machines (TBM), are located approximately 60 feet below ground level, have a diameter of 5.5metres and are 5metres apart.[23][24][25][26][27] [28] A total of 6 TBMs were used for work in the underground section of phase I. They were nicknamed Helen (TBM 1), Margarita (TBM 2), Kaveri (TBM 3), Krishna and Godaveri.[29]

The progress on the underground connection between Reach-1 and Reach-2 was delayed and temporarily put on hold, due to a controversy created by a statue of Dalit leader Ambedkar, as it stood above the planned metro rail line near Bangalore's Vidhan Soudha. Dalit groups had opposed shifting of the statue, while the government had sought to avoid controversy by not following court orders to temporarily shift the statue while construction continues. The controversy delayed the project by six months and caused delays to the north-south reaches which plan to use the Majestic interchange.[30][31]

Underground UG2 (east to west corridor) tunneling work on this 18.1 km was completed on 17 March 2014 after tunnel boring machine Helen (TBM 1) finished its task of tunneling 229m between Bangalore City railway station underground (UG) station and Kempegowda UG station (Majestic). Now, the twin tunnels between Cubbon Park UG station and City Railway Station UG station are ready for track laying and other related works.[32]

Phase II

The detailed project report (DPR) for Phase II was prepared by the Delhi Metro Rail Corporation.[33] The high power committee (HPC), in July 2011, gave in-principle clearance to proceed with Phase II.[34] The Karnataka government gave in-principle approval to Phase II of the Namma Metro project on 3 January 2012.[35][36] Phase II was cleared by the expenditure finance committee (EFC) in August 2013.[37] The Union cabinet announced that it has approved plans for phase II on January 30, 2014.[38] The estimated total cost for Phase II is around 264.05 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). billion).[39] Phase II covers a span of 72.095 km – 13.79 km underground, 0.48 km at grade and 57.825 km elevated, and adds 61 stations to the network, of which 12 are underground.[40] Construction of the second phase will begin in 2014, after completion of the first phase.[41] On 28 February 2014, the Chief Minister Siddaramaiah said the work will be completed within five years.[42]

Phase 2 will include extension of Phase 1 corridors as well as the construction of two new lines. Proposed work includes a 13.9-km underground stretch in the new 21.25-km Gottigere–Nagawara line.

The corporation has already begun the process of identifying land required for viaducts and coordinating with the Karnataka Industrial Area Development Board (KIADB) to issue the land acquisition notifications.

Phase II consists of extensions for all four reaches of the metro and two new lines.[43]

File:Namma Metro Phase II Line Map.png
Proposed new lines and extensions to existing lines – under Phase 2
Line Terminals Length New Stations Expected Work Completion date
Purple Line Mysore Road – Kengeri 6.465 km 5 December 2019
Purple Line BaiyyappanahalliWhitefield 15.50 km 14 December 2019
Green Line Puttenahalli – Anjanapura 6.29 km 5 December 2019
Green Line Hesaraghatta cross – BIEC 3.77 km 3 December 2019
Line 3 R V Road – Bommasandra 18.80 km 16 December 2019
Line 4 Gottigere – Nagavara 21.25 km 18 December 2019
[44]

The project cost of 264.05 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). billion) is the 2011–12 price level, which it is set to escalate at 5 per cent every year with increasing cost of inputs. The Union government will share that part of cost escalation due to increase in central levies, while the Karnataka State and BMRCL have to bear any other escalation. According to the experts, the total project cost for Phase II is estimated to reach at least 300.00 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). billion) at the start of construction itself.

Phase III

The detailed project report (DPR) for Phase III is being prepared by RITES. 133 km phase 3 of metro will connect Nagawara and Kempegowda International Airport (KIA) by a 25-km line; Sarjapur Layout (station, Carmelaram) and Yelahanka (station, Kogilu Road Cross) by a 35-km line covering Central College, Palace Guttahalli, Mekhri Circle and Hebbal; and a 17-km line from the Nice Ring Road to Toll Gate via Magadi Road.

Airport high-speed rail link from CBD

There was a proposal to build a 33 km line known as Bangalore High-Speed Rail Link, from MG Road to Bengaluru International Airport (BIA), at a cost of 57.67 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million).[45] Previously, there was plan for an independent body, but later it was decided that BMRC will manage this project.[46]

This project has now been scrapped keeping in mind its viability and cost. An airport metro extension from Nagavara to BIAL might be considered for inclusion in Phase III.

Opening

Namma Metro was originally scheduled to begin operations in March 2010. Deadlines for completion were repeatedly missed,[47] and the metro was finally opened to the public on 20 October 2011 by Union Urban Development Minister Kamal Nath.[48] There was an overwhelming response to the metro at the commencement of operations. As per BMRCL sources within first 3 days of operations 169,019 people used this mass transit system.[49] At the end of 4th day about 200,000 passengers had already commuted in Namma Metro. Namma Metro's first 12-day cumulative revenue was 10 million (US$160,000).[50]

The State Government removed N Sivasailam as MD of Namma Metro on 10 August 2013. He was replaced by Pradeep Singh Kharola.[51][52][53] The Green Line (Reach 3, 3A & 3B) was initially scheduled to be opened for the public by the end of 2012. However, according to the BMRCL, because of the time taken by the Indian Railways to approve works at Swastik Station and Malleswaram 66-metre metro viaduct, the Green Line was expected to open only in April–May 2013. However, the timelines were delayed further.[citation needed]

The line was opened to the public at 6 am on 1 March 2014.[54] BMRCL Managing Director Pradeep Singh Kharola stated that about 25,000 passengers travelled on the line on opening day.[55] In the first month of operations, 7.62 lakh people at an average of 24,605 people daily used the line, generating a revenue of 1.5 crore (US$240,000).[3]

Network

Namma Metro is being built in phases. Phase I of Namma Metro covers a total of 42.30 km and will be completed by the end of 2015. Phase II spans a length of 72.1 km. The entire network after completion of phase 2 is as given below.

Line First operational Last extension Stations Length
(km)
Terminals
Purple Line 20 October 2011 36 34.3 Whitefield Kengeri
Green Line 1 March 2014 1 May 2015 32 40.1 BIEC Anjanapura
Line 3 16 18.8 R V Road Bommasandra
Line 4 18 21.2 Gottigere Nagavara
Total 102 114.4

Purple Line

The Purple Line will connect Baiyappanahalli in the east to Mysore Road in the west, covering a distance of Script error: No such module "convert".. It is partly elevated, partly underground and has one station at grade. The inauguration of the first stretch between Baiyappanahalli and M.G. Road was on 20 October 2011.

Green Line

The Green Line will be the second line of the Metro to be opened and will connect Nagasandra in the north to Putenhalli in the south, covering a distance of Script error: No such module "convert".. It is partly elevated, partly underground and has one station at grade. The first stretch to open is the 9.9 km long Reach 3 and Reach 3A. The stretch connects Swastik to Peenya Industrial Area.[56]

Finances

Funding

The Union Cabinet approved Phase I of the Namma Metro in April 2006 when it was estimated to cost 54 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million). The cost escalated to 116.09 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). billion) as various problems delayed the completion.[57] BMRCL received 7 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million) from Housing and Urban Development Corporation Limited (HUDCO), 250 million (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million) from the Asian Development Bank (ADB), 23% from the Central Government, 33% from the State Government and the rest as a 49.05 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million) loan from the Japan International Cooperation Agency (JICA).[58][59]

On 3 January 2012, the Karnataka government approved a budget of 270 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). billion) for Phase II of Namma Metro project. It was initially expected to cost around 250 billion (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). billion).[60] On 27 March 2012, the Asian Development Bank (ADB) signed an agreement to lend $250 million to BMRC to part-finance Phase II of the metro rail project. The loan marked the multilateral lending agency's foray into the urban transport sector in South Asia, the ADB said in a press release.[61] The loan, approved by the ADB Board in March 2011, is the first ADB loan to the urban transport sector without recourse to sovereign guarantees.[62] The State and Central Governments will bear 30% and 20% of the project cost of Phase II respectively. The remaining amount will be obtained through senior term loans.[63]

BMRCL announced plans on 13 June 2013 to issue 10-year bonds.[64] The proposed bonds received a credit rating of "IND AA" from India Ratings & Research (Ind-Ra),[65] a Chennai-based research company.[66] Namma Metro MD N. Sivasailam announced on 3 August 2013 that the issue of bonds would be postponed as the market was volatile. Sivasailam stated that the metro would "be in the market soon and when it is stable."[67]

Revenues and Profits

During the first month, since the opening of Reach I, about 1325,000 people travelled by the metro.[68] On average, 41,390 people took the train every day, while the average daily revenue was 667,262. The BMRC earned a revenue of 21 million (US$330,000) in its first month of operation.[69] In the first six months of operation, average ridership went down to 24,968. The BMRC earned a total of 66 million (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million) during the same period.[70]

Namma Metro posted a profit of 4.1 million (US$65,000) after almost one year of operating Reach I. BMRCL estimates that nearly 8 million passengers travelled on the system, in its first year of operations.[71]

Infrastructure

File:Namma Metro.jpg
Purple Line train
File:Namma Metro coach interior.jpg
Interior of the Metro coach
File:Metro first day rush.jpg
Interior of the Metro coach on inauguration day
File:Namma Metro Station.jpg
MG Road Station at night

Rolling stock

The specification for rolling stock is based on stainless steel-bodied three-car formations, a trailer between two motored driving units. Internal wide gangways provide ease of passenger movement and assist in load distribution. Trains are air-conditioned throughout with designated space for disability access. Although with many automated functions, trains are under driver control.

The capacity per train is approximately 1,000 through longitudinal seating, giving a high proportion of the floor area to standing passengers. The maximum attainable speed is Script error: No such module "convert"..[citation needed]

Initially the bids by Bombardier and Siemens, Alstom Projects India Ltd and consortium comprising BEML, Mitsubishi and Hyundai Rotem were shortlisted to supply the rolling stock and coaches. In February 2009, the BEML-led consortium was awarded the contract to supply 150 coaches and rolling stock for the first phase of the project. While Mitsubishi would supply the traction for the coaches, Hyundai Rotem would supply the rolling stock and BEML would supply the coaches for Phase I.[72]

The first trainset made a trial run in December 2010.[73]

Track gauge: Bangalore metro uses standard gauge unlike Delhi Metro. But, the recent studies[by whom?][citation needed] have found that broad-gauge is suited for Indian conditions as well as long term economical feasibility as India has growing population. Indian metro trains with standard gauge does not provide seating facility and favoured towards standing travel. Ahmedabad Metro has chosen driverless technology and broad gauge as it provides comfort to the passengers.[74] Bangalore metro has not migrated from standard gauge to broad gauge for new lines in the Phase-2 or Phase-3 of the project. It has however, as a reply to an RTI application, defended the decision to use Standard Gauge.[75]

All metro trains are Wi-Fi enabled (the first metro in India to have this feature), so passengers can use laptops, tablets as well as mobile internet.[76] The free Wi-Fi service was made available to commuters on 31 July 2013.[77] Passengers also have emergency voice communication with train staff through a speaker system. Passengers are provided with a call button to communicate anything to the driver or control center during an emergency.[76] Yellow textured tiles are used at all stations to guide the visually impaired through the station.[78]

Power supply

The power for the system is 750 V DC bottom contact third rail supply. In December 2009, the ABB Group was awarded the contract to provide power solutions for the first phase of the planned metro network. ABB will design, supply, install and commission four substations that receive and distribute electricity, each rated at 66/33 kV, as well as the auxiliary and traction substations. ABB will also provide an integrated network management, or SCADA (Supervisory Control And Data Acquisition), system to monitor and control the installations.[79]

Signaling

In September 2009, the consortium led by Alstom Project India Limited were awarded a contract worth 5634 million (US$Lua error in Module:Math at line 495: attempt to index field 'ParserFunctions' (a nil value). million) to supply control and signalling system for the first phase of the project. The consortium is led by Alstom and composed of Alstom Transport SA, Thales Group Portugal S A and Sumitomo Corporation. Alstom will provide the design, manufacture, supply, installing, testing and commissioning of the train control and signalling system and Thales will provide the design, installing, testing and commissioning of the telecommunication system for Phase I of the metro system. It includes the Urbalis 200 Automatic Train Control system which will ensure optimal safety, flexible operations and heightened passenger comfort.[80][81]

Most of the cables used in the signalling system are steel armoured. UPS provided at at stations as well as for OCC ensures uninterrupted power for signaling and communication. Points are operated with 110V D.C. point machines and 380 volts 3 phase, 50 Hz. AC point machines. Audio frequency track circuits are installed on the running section, test track and in depot. Signalling along the line is done through ATC with line side signal as fall back. All data transmission is carried out on telecom cables/OFC/Radio, and all signalling and telecom cables are separated from power cables to make the system immune to external interference. The signalling system of the Namme Metro complies with SIL4 level safety.[82]

Line Side Signalling and Train protection

Line Side Signalling and Train protection is the primary function of the train control systems. This sub-system is intended to be inherently capable of achieving the following objectives in a fail-safe manner:

  • Prevent rear-end or side collision resulting from one train trying to over-take the other.
  • Prevent trains being routed on the conflicting routes.
  • Prevent the possibility of points / switches moving just ahead of or under train.
  • Not hindering the vehicles attaining maximum permissible speed.

The basic sub-system includes the following modules - Train detection, Train Protection, Solid State Interlocking, Signal and speed enforcement, Brake assurance, and Interface with electrical sub-systems of the vehicle like brake control. Track circuits/balise are used for vehicle detection. Sub-system/components conform to international standards such as BS, IS, IEC, ITU-T etc. The cab borne signalling equipment are of modular sub-assemblies for each function for easy maintenance and replacement. The Automatic Train Protection (ATP) assemblers are fitted in the vehicle integrated with other equipment of the rolling stock.[82]

Solid State Interlocking

At all stations with points and crossings, Solid State Interlocking (SSI) is provided for operation of points and crossings and setting of routes. Six SSIs are provided on Purple Line and five on the Green Line. This sub-system is used for controlling vehicle movements into or out of stations automatically from a work station. All stations having points and crossings will be provided with workstations for local control. Track occupancy, point position, etc. will be clearly indicated on the workstation. The setting of the route and clearing of the signals is also done by the work station. It is possible to operate the workstation locally, if the central control hands over the operation to the local station. The system design will be on the basis of fail- safe principle. The equipment will withstand tough environmental conditions encountered in a Mass Transit System. Control functions in external circuits will be proved both in the positive and negative wires. Suitable IS, IRS, BS standards or equivalent international standards will be followed in case wiring, installation, earthing, cabling, power supply and for material used in track circuits, relays, point operating machines, power supply etc. The depot for Purple Line is situated at Baiyyappanahalli and that for Green Line at Yeshwanthpur. Each depot / workshop yard except the lines mainly used for shunting is interlocked. A work station is provided in the Depot Control Centre for electrical operation of the points and signals of the depot yard.[82]

Automatic Train Protection

To ensure safety in train operation and to provide optimum train services on the section, the train control on the metro is provided with Automatic Train Control system. For this the transmission from track to train will be continuous through coded audio frequency track circuit. The ATC system provides on-board display of maximum safe speed, current speed and target speed / distance as deduced from ATP systems, signaling interlocks systems and based on track profile and brake characteristics. Facilities for automatic enforcement of temporary / permanent speed restrictions were also built in to enhance safety during maintenance work. At all stations, electronic passenger information display boards are provided. The PIS is train actuated along with facility to be automatically inputted from the local station.[82]

Train describer system

A train describer system will be installed to facilitate the monitoring of train operation and also remote control of the stations .The train describer will log each train movement and display it on the workstations with each Traffic Controller at the OCC and on one workstation placed in the Station Control room (SCR) with each Station Controller. The system will be installed in the Operation control center and at the stations with point and crossings and will have a panoramic view of the sectional jurisdiction showing the status of tracks, points and the vehicles operating in the relevant section/ whole system. The system shall provide train information in real time and in hard copy for later analysis. It shall be possible to set route of trains at terminals, mid-terminals and runback stations, etc. both locally and remotely. It shall have audio-visual alarms for deficiencies / malfunctioning.[82]

Communications

The telecommunication facilities are intended to supplement the signalling system for efficient train operation, exchange managerial information, for crisis management during emergencies and facilitate the passenger information system.[82]

The main bearer of the bulk of the telecommunication network is an optical fiber cable system. Considering the channel requirement and keeping in view the future expansion requirements optical fiber cable was laid in ring configuration with path diversity. Apart from meeting required optical characteristics, it will be low smoke/ low halogen type optical fibre cable. SDH STM-1 155 Mb based system were adopted with SDH nodes at every station, OCC and depot. Access 2MB multiplexing system was adopted for the lower level at each node, equipped for channel cards depending on the requirement of channels in the network. Further small routers and switches were provided for LAN network at station. Three EPABX of 512 ports were provided at three locations - one at the OCC, one at an intermediate station and other at the depot - to serve as telephone exchanges. The Telephone Exchanges serve the subscribers at all the stations, OCC and depot. The exchanges are interconnected at multiple 2 MB level through optical fibre cable. The Exchanges are software partitioned for EPABX and Direct Line Communication from which the phones are extended to the stations.[82]

Mobile Radio communication system having 8 channels is used for on-line emergency communication between Motorman (Front end and Rear end) of moving train and the Central Control. The system is based on Digital Trunked Radio Technology to TETRA International standard. All the stations and Car Depot are provided with fixed radio sets. Mobile communication facility for maintenance parties and Security Personnel is provided with handheld sets. These persons are able to communicate with each other as well as with central control. To provide adequate coverage, based on the RF site survey, base stations for the system are located at a site conveniently selected after the detailed survey. Radio Base stations, interlinked to the Central Radio Equipment at the OCC through channels on the optical fibre system are provided. The frequency band for operation of the system were that for TETRA in 400/800 MHz band depending upon availability of frequency. Instant mobile radio communication between the motorman of the moving cars from any place and the Central Control can be established. The motorman can also contact any station in the network through the central control, besides intimating the approaching trains about any emergency like accident, fire, line locked etc., thus improving safety performance.[82]

The Passenger Announcement System can make announcements from the local station as well as from OCC. Announcements from OCC have over-riding priority in all announcements. The Centralized Clock System ensures an accurate display of time through a synchronization system of slave clocks driven from a Master Clock at the operation control center. The Master Clock signal is also required for synchronization of SDH and Exchanges. The system ensures identical display of time at all locations. Clocks are provided at platforms, concourse, Station Master's Room and other service establishments. LED based boards with adequate visibility located at convenient locations at all stations to provide bilingual visual indication of the status of the running trains and will typically indicate information such as destination, platform numbers, arrival/departure time, and also special messages in emergencies. The boards are provided at all platforms and concourses of terminal and junction stations.[82]

For efficient and cost effective maintenance of the entire communication network, a network management systems (NMS) was provided. The NMS helps in diagnosing the faults immediately from a central location and attending the same with least possible delay, thus increasing the operational efficiency and reduction in manpower requirement for maintenance. The NMS system covers radio communication, Optical Fiber Transmission system and Telephone Exchange.[82]

The integrated control centre at Byappanahalli has direct communication with trains and stations are CCTV fitted with visual and audio service information.[76] Passengers have emergency voice communication with train staff.

Stations

The basic planning for stations developed for the Delhi Metro, was used to plan Namma Metro stations. However, the size of Namma Metro stations is smaller than that of Delhi. Stations have been designed to fit in the existing road width as far as possible. There are 36 stations of the Purple Line of which 4 are underground and 1 is on the surface. The Green Line has 24 stations of which 3 are underground and 1 is at grade. The remaining stations on both the corridors are elevated. Stations located on the middle of the road have been designed with elevated concourse with access from both sides of the road. All the elevated stations are provided with side platforms while the underground stations are provided with island platforms. This was done to facilitate continuous construction of the elevated section carrying two tracks, and to avoid reverse curves on the approaches of the stations. For the underground sections, Tunnel Boring Machines (TBMs) work effectively with tunnel centers equivalent to two times the tunnel diameter thus providing sufficient space for platform in between. All the underground stations were constructed by the cut and cover method. Majestic station located in the KSRTC bus stand area is common to both lines and serves as an interchange station. A link line between the two corridors is also provided at this station for transfer of rakes. The average inter-station distance along the corridors is 1 km, with minimum distance being 0.676 km, and maximum being 2.04 km.[7]

Stations have been divided into two distinct areas, namely public and non-public (technical areas). The public area is further sub divided into unpaid and paid areas. Provisions for escalators are made at all stations in the paid area. However, at a few important stations escalators are provided from the beginning itself. Lifts for disabled passengers are provided at all stations except at Baiyappanahalli where ramps are provided. Road traffic integration facilities are provided at 5 stations on the Purple Line - Mysore Road, Hoshalli, Bangalore City metro station, Majestic and Ulsoor. On the Green Line integration facilities are provided at Yeshwantapur, Swastik, Majestic, City Market and R V Road terminal. Integration facilities at metro stations include approach roads to the stations, circulation facilities, pedestrian ways and adequate parking areas for various modes likely to come to important stations including feeder buses/mini buses. Provisions were also made for peak hour demand.[7]

Initially, there were no toilets at Namma Metro stations, despite demand from commuters. BMRCL countered the demand by arguing that constructing toilets was not part of the metro construction plan, and that building toilets in the city was the responsibility of the Bruhat Bengaluru Mahanagara Palike (BBMP). They also justified the decision by saying that commuters spent "hardly five minutes" at stations, so restrooms were not required, and also that none of the Bangalore Metropolitan Transport Corporation (BMTC) bus stops in the city had toilets for passengers. However, BMRCL eventually heeded public demand, and the metro's first toilets were opened at Baiyappanahalli and Indiranagar stations on 21 June 2013.[83]

Safety

As of February 2014, BMRCL has two road-cum-rail rescue vehicles that can be used to perform evacuations or re-load derailed trains back onto the track.[84]

The trains are equipped with derailment prevention equipment, and the tracks are equipped with concrete barriers to prevent trains from leaving the viaduct. The support pillars are earthquake proof and are designed to have a lifespan of at least 100 years. Trains are equipped with sensors to detect impending collisions, and have automatic braking systems to prevent speed limits from being exceeded.[85]

Depots

As the Purple and Green Lines are interlinked, rakes can move from one corridor to another for Intermediate Overhaul (IOH) and Periodical Overhaul (POH). This facilitated the construction of one mother workshop for the two corridors at Baiyappanahalli. An inspection shed, which has the stabling facilities at Baiyappanahalli and one inspection shed having stabling facilities at Yeshwantapur on the Green Line were constructed. Adequate facilities for the stabling are provided at the terminal stations as well as at the depots. All the minor maintenance schedules would be independently taken over in each corridor thus saving the idle run of trains for the minor maintenance. For the IOH and POH the rakes would be taken to the mother workshop.[86]

Rainwater harvesting

BMRCL, in a public-private partnership, harvests rainwater from the viaducts on the rail system. The private partner, Karnataka Rural Infrastructure Development (KRIDL), collects the water at multiple points, treats it, and sells it in bulk as potable water.[87] Around 80 million litres of water are expected to be collected annually.[88]

BMRCL also plans to harvest rainwater from the 140 acre depot facility at Peenya. Water will be collected from the 190,000 sq foot roof and stored in two tanks with a capacity of 50,000 litres each. Rainwater harvesting is also planned in the existing and under-construction stations. The water harvested will be supplied to places where needed, and any excess will be used for groundwater recharge.[88]

BMRC has installed a water harvesting system along Reach 1 and will be doing the same for Reaches 3 & 4. Installation of flower beds was delayed due to garbage being dumped on the median by garbage collectors, BMRC will also set up flower beds on Reach 1 with assistance from the horticulture department. However, the work related to this has slowed down due to garbage contractors dumping garbage along the median, due to the lack of a waste management plan in the city.[89] BMRC will rejuvenate Kengeri and Veerasandra lakes using water collected from a nearby corridor.[90][91]

Operations

Fare collection

File:Bangalore metro token front.jpg
The obverse of an entry token issued
File:Bangalore Metro Ticket(Token)-View2.jpg
Bangalore Metro Ticket(Token)-Kempegowda Tower Symbol view

MIFARE DESFire platform, developed by NXP Semiconductors, was selected to manage the Automated Fare Collection (AFC) in Namma Metro.[92] There are three types of computer controlled automatic gates on the metro system - entry gates, exit gates and reversible gates (can be set to entry or exit). There are also disabled gates which are wide reversible gates for the disabled). All the fare collection equipments are connected in a local area network with a station server controlling the activities of all the machines. These station servers are linked to the central computer situated in the operational control centre through the optic fibre communication channels. The centralized control of the system provides real time data of earnings, passenger flow analysis, blacklisting of specified cards etc.[93]

Namma Metro uses contactless smart tokens and contactless smart card.[94] Tokens are available only for single journey. They have a stored value amount for a particular journey, and are captured at the exit gate.[93] A person can buy up to 6 tokens for additional five passengers and himself.[citation needed] Smart cards can be used for multiple journeys.[93] There are 4 types of smart cards available on the metro – Varshik, Sanchar, Saral and Saraag.[95]

  • Varshik is priced at 100. It is valid for a year, and provides a 15% discount on fares. The card can be recharged.
  • Sanchar is available in denominations of 10, 40, 50 and 100.
  • Saral costs 70. It permits one day's travel on BMTC non-air-conditioned buses and on the metro.
  • Saraag costs 110. It permits one day's travel on BMTC air-conditioned buses and on the metro.[96]

BMRCL began selling tokens through automatic ticket vending machines (ATVMs) on 4 December 2012 at MG Road, Indiranagar and Baiyyappanahalli stations. The service will eventually be expanded to all metro stations. The touchscreen enabled ATVMs are available in 3 languages – English, Kannada and Hindi. Commuters can purchase a single journey token by selecting the destination station or the amount in the ATVM. They can also add value or add trips to the tickets in the contactless smart card. Commuters can purchase up to 8 tickets at a time and can get the receipt print for card recharge. ATVMs accept coins of 5 and 10 denominations and 10, 20, 50, 100, 500 and 1,000 denominations of currency notes. However, the ATVM cannot differentiate between 1 and 2 coins.[97][98]

Approximately, 68% of passengers on the metro use smart tokens and 32% use smart cards.[71]

Frequency

The metro service runs between 0600 and 2200 hours. There are trains every 15 minutes between 0600 and 0800, 10 minutes between 0800 and 2000, and 15 minutes between 2000 and 2200.[99] The frequency is slated to increase to once every three minutes by 2021. The travel time from end to end on the Purple Line will be 33 minutes, and on the Green Line will be 44 minutes.

Metro services have occasionally operated beyond 2200 hours. Services are usually extended on festival days or when a major cricket match is held in Bangalore.[100][101]

Speed

The system is designed for a maximum train speed of 80 km/h. However, the Research Design and Standards Organization (RDSO) fixed the speed at which trains are allowed commercially operate at 67.50 km/h on straight sections, 35 km/h on curves, and 45 km/h in stations.[102]

Ridership

Reach 1
The average daily ridership of Reach 1 of Namma Metro is 24,968. The Metro’s highest recorded ridership was 85,004, on 23 October 2011, the Sunday following the service’s inauguration.[70]

Reach 1, 3 and 3a
Now, the average daily ridership of Reaches 1, 3 and 3a of Namma Metro is 110,000.

Laws

The Bangalore Metro Rail (Carriage and Ticket) Rules 2011 limit the weight of personal baggage to 15 kg. Rule 3 says: “No person shall, while travelling in metro railway, carry with him any goods other than a small baggage containing personal belongings not exceeding 60cm x 45cm x 25cm in size and 15kg in weight, except with the prior approval of the metro railway administration.” The rules also prohibit carrying explosive, inflammable, and poisonous substances.[103]

The Metro Railway (Operation and Maintenance) Act, 2002, imposes fines and in some cases jail sentences for offences committed on the metro. Anyone indulging in sabotaging the train or maliciously hurting or attempting to hurt other passengers while travelling in the metro can face imprisonment up to 10 years. Pasting posters or drawing graffiti on the walls of stations or trains is punishable by a fine of 1,000 or imprisonment for up to 6 months. Travelling in an inebriated state or creating nuisance in the train is punishable by a 500 fine.[104] Passengers are monitored at security checkpoints and those that are causing trouble, heavily drunk, or carrying forbidden items are not permitted to board.[105] Spitting on the metro premises is punishable by a fine of 100.[106]

Security

Currently baggage is manually searched by security guards hired by BMRCL. Bangalore City Police are in charge of external security of metro installations. Plans are underway to install three baggage scanners each at Baiyappanahalli, Swami Vivekananda Road and Indiranagar stations and two each at M.G. Road, Trinity and Halasuru stations. There are attendants and multiple security guards on each platform, and photography is strictly prohibited.[107]

Fatalities

On 5 March 2012 at 8:35 pm, a 16-year-old boy threw himself under a train at the MG Road station. The boy was identified as S Vishnu Sharan, a first-year student of St. Joseph's PU College and a resident of Jayanagar. This was the first death to occur after Namma Metro operations began.[108]

Gallery

See also

Lua error in package.lua at line 80: module 'Module:Portal/images/i' not found.

References

  1. ^ a b "Project Highlights". Official webpage of B.M.R.C. Retrieved 3 May 2010. 
  2. ^ "Metro gets $250m for next phase". The Times of India. 28 March 2012. 
  3. ^ a b "Byappanahallimg road metro stretch more popular". The Hindi. 
  4. ^ "BMRCL to issue bonds to raise Rs. 500 crore". The Hindu (Chennai, India). 14 June 2013. 
  5. ^ "Namma metro to chug on October 20 – southindia – Bangalore – ibnlive". Ibnlive.in.com. Retrieved 21 October 2011. 
  6. ^ http://www.deccanherald.com/content/389661/25000-ride-green-line-metro.html
  7. ^ a b c d e f g h i j Delhi Metro Rail Corporation Ltd, assisted by RITES Ltd (May 2003). "Detailed Project Report (Final), Bangalore Metro (Phase I)". esgindia.org. Retrieved 30 May 2015.  15px This article incorporates text from this source, which is in the public domain.
  8. ^ "A K Bhattacharya: A tale of two Metros". Business Standard. 15 July 2012. Retrieved 25 July 2012. 
  9. ^ http://bmrc.co.in/pdf/phase2/phase2forweb.pdf
  10. ^ "A city begins to fulfill a Metro dream". The Indian Express. 20 October 2011. Retrieved 3 January 2012. 
  11. ^ Delhi Metro Rail Corporation Ltd, assisted by RITES Ltd (May 2003). "Detailed Project Report (Final), Bangalore Metro (Phase I)" (PDF). esgindia.org. p. 7. Retrieved 30 May 2015. 
  12. ^ "Bangalore Metro:Metro Network". Archived from the original on 2015-03-15. 
  13. ^ (Press release). The Indian Express. 2 March 2015 http://www.newindianexpress.com/cities/bengaluru/Metro-to-Chug-Through-Tunnel-Next-Week/2015/03/02/article2693883.ece.  Missing or empty |title= (help)
  14. ^ http://www.newindianexpress.com/cities/bengaluru/Metro-to-Chug-Through-Tunnel-Next-Week/2015/03/02/article2693883.ece
  15. ^ "Metro Reach 3B to be opened on May 1". 24 April 2015. 
  16. ^ http://www.business-standard.com/article/companies/bangalore-metro-ph-1-completion-pushed-to-q1-2016-114092200747_1.html
  17. ^ "Indian cabinet approves the project". Online Edition of The Economic Times. 28 April 2006. [dead link]
  18. ^ "Award of contract" (PDF). Official webpage of B.M.R.C. Retrieved 2 October 2011. [dead link]
  19. ^ "PM lays foundation stone for Metro project". PM office website. 
  20. ^ "Bangalore Metro Rail Work to begin on Feb 3, 2007". The Times of India. 21 January 2007. Retrieved 16 October 2007. 
  21. ^ http://timesofindia.indiatimes.com/city/jaipur/Jaipur-Metro-completed-in-record-time-but-limping-in-commercial-run/articleshow/47137986.cms
  22. ^ "GOK order on Metro Extension" (PDF). Official webpage of B.M.R.C. Retrieved 26 November 2008. 
  23. ^ Rohith B R, Bangalore, 14 Oct 2012, DHNS: (14 October 2012). "Automation helps precise work on metro tunnels". Deccan Herald. Retrieved 4 March 2013. 
  24. ^ RohithB R, Bangalore, 13 Oct 2012, DHNS : (13 October 2012). "Metro makes steady inroads". Deccan Herald. Retrieved 4 March 2013. 
  25. ^ Special Correspondent (28 September 2012). "A smoother passage for Margarita". The Hindu (Chennai, India). Retrieved 4 March 2013. 
  26. ^ Bangalore, 23 Sep 2012, DHNS : (23 September 2012). "Tunnelling along north-south corridor to begin soon". Deccan Herald. Retrieved 4 March 2013. 
  27. ^ Update : 06:47 pm IST (18 December 2012). "Metro rushes to meet deadline". Deccan Chronicle. Retrieved 4 March 2013. 
  28. ^ Bangalore, 21 Feb 2013, DHNS (21 February 2013). "After Helen, Margarita, it's Krishna and Kaveri". Deccan Herald. Retrieved 4 March 2013. 
  29. ^ http://www.deccanchronicle.com/150106/nation-current-affairs/article/2015-be-milestone-year-namma-metro
  30. ^ Update : 06:47 pm IST (4 January 2013). "Namma Metro: Frozen in its tracks". Deccan Chronicle. Retrieved 4 March 2013. 
  31. ^ Mehrotra, Akanksha (4 January 2013). "Citizen Matters, Bangalore: 2013: Will Bengaluru’s Metro expand from a minuscule 6km ?". Bangalore.citizenmatters.in. Retrieved 4 March 2013. 
  32. ^ "Tunnelling work on metro corridor completed". The Hindu. 18 March 2014. 
  33. ^ "State Cabinet approves phase-II of metro". Business Standard. 4 January 2012. Retrieved 6 March 2012. 
  34. ^ "Metro project: Cabinet approves two new lines for Phase 2". The Times of India. 4 January 2012. 
  35. ^ Bangalore, 4 Jan, DHNS:. "Centre's nod for Phase-II of Metro may take 6 months". Deccan Herald. Retrieved 6 March 2012. 
  36. ^ "Cabinet clears Namma Metro Phase 2 – Bangalore – DNA". Daily News and Analysis. 4 January 2012. Retrieved 6 March 2012. 
  37. ^ Neha Sethi, Rahul Chandran (2013-09-05). "EFC clears `26,405 cr for Bangalore Metro phase II". Livemint. Retrieved 2013-09-28. 
  38. ^ IRJ, 30 Jan; (30 January 2014). "Go-ahead for Bangalore metro phase 2". 
  39. ^ "Cities / Bangalore : Frame policy for differential fare pricing, BMRCL told". The Hindu (Chennai, India). 22 February 2012. Retrieved 6 March 2012. 
  40. ^ "Metro gets poll push for Phase II". Deccan Chronicle. 2013-06-04. Retrieved 2013-09-28. 
  41. ^ "Second phase of Bangalore Metro project cleared". IBN Live. Retrieved 6 March 2012. 
  42. ^ "Sampige Road-Peenya Metro Line Inaugurated". The New Indian Express. 1 March 2014. Retrieved 8 September 2014. 
  43. ^ "Metro project: Cabinet approves two new lines for Phase 2". Times Internet. 4 January 2012. Retrieved 8 September 2014. 
  44. ^ "Green signal for Metro's Phase II". The Times of India. 22 February 2012. Retrieved 6 March 2012. 
  45. ^ "Metro project: Cabinet approves two new lines for Phase 2". The Times Of India. 4 January 2012. [dead link]
  46. ^ "Metro will have high-speed link to BIA". The Times of India. 21 October 2011. 
  47. ^ "Bangalore Metro misses deadline for 4th time, minister sets Sept 26 as next date : South, News". India Today. 16 September 2011. Retrieved 8 September 2014. 
  48. ^ "Metro comes to Bangalore finally". The Times of India. 20 October 2011. Archived from the original on 20 October 2011. 
  49. ^ "Revenue Services Report" (PDF). 
  50. ^ Madhumathi D.S. "Business Line : Industry & Economy / Logistics : Namma Metro rides on 'gawk' power". Business Line. Retrieved 3 January 2012. 
  51. ^ "Namma Metro Man Sivasailam shifted". The Times Of India. 11 August 2013. 
  52. ^ News, Express (2013-08-11). "Sivasailam shunted out of BMRCL". The New Indian Express. Retrieved 2013-09-28. 
  53. ^ "Pradeep Kharola is new Metro chief - Bangalore - DNA". Dnaindia.com. Retrieved 2013-09-28. 
  54. ^ Special Correspondent (2014-02-28). "CM in a hurry, delays Namma Metro launch". The Hindu. Retrieved 2014-03-27. 
  55. ^ "25,000 ride Green line Metro on 1st working day". Deccan Herald. 2014-03-03. Retrieved 2014-03-27. 
  56. ^ "Rajajinagar, Peenya residents can smile – The Times of India". The Times of India. 28 November 2011. 
  57. ^ "It's official: Namma Metro Phase-1 not before 2014". Deccan Chronicle. 21 December 2011. Retrieved 3 January 2012. 
  58. ^ "Namma Metro Phase II requires Rs. 25,000 crore – southindia – Hyderabad – ibnlive". Ibnlive.in.com. Retrieved 21 October 2011. 
  59. ^ "Metro rail projects: Four new metromen and their challenges – Economic Times". The Economic Times. 18 December 2011. Retrieved 3 January 2012. 
  60. ^ "Admin approval for Namma Metro Phase II – South India – Karnataka – ibnlive". Ibnlive.in.com. Retrieved 6 March 2012. 
  61. ^ "View source for Namma Metro – Wikipedia, the free encyclopedia". En.wikipedia.org. Retrieved 25 July 2012. 
  62. ^ "Bangalore Metro gets $250 mn ADB loan". Business Standard. 28 March 2012. Retrieved 25 July 2012. 
  63. ^ Bangalore, 17 Oct 2012, DHNS : (17 October 2012). "Centre's nod awaited to extend Metro to Bengaluru Intl Airport". Deccan Herald. Retrieved 4 March 2013. 
  64. ^ "B'lore Metro to raise Rs 300 cr via bond issue". Business Standard. 2013-06-11. Retrieved 2013-09-28. 
  65. ^ Anil Urs (2013-06-14). "‘IND AA (exp)’ rating for Bangalore Metro proposed bonds | Business Line". Thehindubusinessline.com. Retrieved 2013-09-28. 
  66. ^ "BMRC proves merit in investment ratings". The Times Of India. 
  67. ^ "BMRCL defers issue of bonds citing market volatility". The Hindu (Chennai, India). 4 August 2013. 
  68. ^ "13.25 lakh rode the Metro – The Times of India". The Times of India. 25 November 2011. 
  69. ^ "Namma Metro gains momentum – southindia – Bangalore – ibnlive". Ibnlive.in.com. Retrieved 3 January 2012. 
  70. ^ a b "Joyrides in Bangalore Metro are over – Bangalore – DNA". Daily News and Analysis. Retrieved 25 July 2012. 
  71. ^ a b "Bangalore Metro posts Rs 41 lakh profit in first year – Bangalore – DNA". Daily News and Analysis. 18 October 2012. Retrieved 18 October 2012. 
  72. ^ "BEML to supply coaches for Bangalore Metro". The Hindu (Chennai, India). 10 February 2009. Retrieved 1 January 2010. 
  73. ^ "Railway Gazette: Bangalore metro trial". Retrieved 13 February 2011. 
  74. ^ http://articles.economictimes.indiatimes.com/2013-07-26/news/40815304_1_ahmedabad-metro-metro-rail-broad-gauge
  75. ^ http://www.bmrc.co.in/pdf/rti1.pdf
  76. ^ a b c "NAMMA-METRO-IS-A-GEEK-TRAIN". The Times of India. 16 October 2011. Retrieved 21 October 2011. 
  77. ^ "Bangalore Metro goes wi-fi". Deccan Chronicle. 2013-08-01. Retrieved 2013-09-28. 
  78. ^ G. Ananthakrishnan (14 January 2013). "Linking modes of commute". The Hindu (Chennai, India). Retrieved 4 March 2013. 
  79. ^ "ABB wins $115 million order to power Bangalore metro". The ABB Group. Retrieved 1 January 2010. 
  80. ^ "Alstom will provide train control and signalling system for the new Bangalore metro network in India". Alstom. Retrieved 2 October 2011. [dead link]
  81. ^ "Alstom-led consortium in pact with Bangalore Metro". Business Standard. 18 September 2009. Retrieved 3 May 2010. 
  82. ^ a b c d e f g h i j Delhi Metro Rail Corporation Ltd, assisted by RITES Ltd (May 2003). [static.esgindia.org/campaigns/Tree%20felling/Hasire%20Usiru/research/Metro_DPR/chp_9_bmrp_dpr.zip "Chapter 9 - Detailed Project Report (Final), Bangalore Metro (Phase I)"] Check |url= scheme (help). esgindia.org. Retrieved 30 May 2015.  15px This article incorporates text from this source, which is in the public domain.
  83. ^ "At Metro, wanna pee? Pay Rs 3 - Bangalore - DNA". Dnaindia.com. Retrieved 2013-09-28. 
  84. ^ http://www.thehindu.com/news/cities/bangalore/bmrcl-launches-roadcumrail-vehicle-for-rescue-operations/article5723229.ece
  85. ^ "'We've taken steps to ensure public safety'". The Times of India. 28 October 2011. 
  86. ^ Delhi Metro Rail Corporation Ltd, assisted by RITES Ltd (May 2003). [static.esgindia.org/campaigns/Tree%20felling/Hasire%20Usiru/research/Metro_DPR/chp_11_bmrp_dpr.zip "Chapter 11: Maintenance Depots - Detailed Project Report (Final), Bangalore Metro (Phase I)"] Check |url= scheme (help). esgindia.org. Retrieved 30 May 2015.  15px This article incorporates text from this source, which is in the public domain.
  87. ^ "'Liquid' cash from viaduct". The Hindu (Chennai, India). 15 December 2011. 
  88. ^ a b Francis, Merlin (2 April 2012). "Namma Metro gets waterwise". DNA India (Bangalore, India). Retrieved 24 June 2012. 
  89. ^ "Metro medians turn garbage dumps". The Times Of India. 6 August 2012. 
  90. ^ TNN url=http://articles.timesofindia.indiatimes.com/2012-11-04/bangalore/34908256_1_n-sivasailam-bmrc-metro-path (4 November 2012). "Lakes to come alive along Metro path". The Times of India. 
  91. ^ "BMRCL plans to rejuvenate lakes, starting with Kengeri – Bangalore – DNA". Daily News and Analysis. 4 November 2012. Retrieved 4 March 2013. 
  92. ^ "Bengaluru Metro System Adopts NXP's MIFARE Technology". MarketWatch. Retrieved 6 March 2012. 
  93. ^ a b c Delhi Metro Rail Corporation Ltd, assisted by RITES Ltd (May 2003). "Chapter 8: Automatic Fare Collection - Detailed Project Report (Final), Bangalore Metro (Phase I)" (PDF). esgindia.org. Retrieved 30 May 2015.  15px This article incorporates text from this source, which is in the public domain.
  94. ^ "Bangalore Metro: Recharge and ride on". The Times of India. 1 January 1970. Retrieved 21 October 2011. 
  95. ^ "Cities / Bangalore : 20,000 smart cards sold for metro ride". The Hindu (Chennai, India). 17 October 2011. Retrieved 21 October 2011. 
  96. ^ "20,000 smart cards sold for metro ride". The Hindu. 17 October 2011. Retrieved 8 September 2014. 
  97. ^ Bangalore, 3 Dec 2012, DHNS : (3 December 2012). "Automatic ticket vending at Metro stations". Deccan Herald. Retrieved 4 March 2013. 
  98. ^ TNN url=http://articles.timesofindia.indiatimes.com/2012-12-05/bangalore/35619832_1_atvms-automatic-ticket-bmrc (5 December 2012). "Yeshwantpur Metro link work picks up pace". The Times of India. 
  99. ^ "Bangalore Metro opens to public at 4 pm on Thursday". The Economic Times. 17 October 2011. Retrieved 21 October 2011. 
  100. ^ Bangalore, 22 Dec 2012, DHNS: (22 December 2012). "Bar timings relaxed for revellers". Deccan Herald. Retrieved 6 June 2013. 
  101. ^ TNN url=http://articles.timesofindia.indiatimes.com/2012-12-24/bangalore/35990901_1_bmrc-namma-metro-2am (24 December 2012). "Metro to run till midnight today, tomorrow". The Times of India. 
  102. ^ Chethan Kumar, Bangalore, 22 May 2013, DHNS: (22 May 2013). "RDSO in no hurry to allow Metro to up speed". Deccan Herald. Retrieved 6 June 2013. 
  103. ^ "Metro gets luggage scanners". Deccan Herald. 
  104. ^ Rohith B R, Bangalore, 18 Oct 2012, DHNS : (18 October 2012). "Commuters' brush with etiquette on Namma Metro". Deccan Herald. Retrieved 6 June 2013. 
  105. ^ url=http://www.deccanchronicle.com/121225/news-current-affairs/article/no-entry-drunk-commuters-metro (25 December 2012). "No entry for drunk commuters in Metro". Deccan Chronicle. 
  106. ^ TNN url=http://articles.timesofindia.indiatimes.com/2012-10-11/bangalore/34385975_1_namma-metro-metro-premises-metro-s-operation (11 October 2012). "Not fine to spit in Metro". The Times of India. 
  107. ^ "Baggage scanners finally arrive at stations". The Hindu (Chennai, India). 1 December 2011. 
  108. ^ "16-yr-old throws himself before Metro train, dies". The Times of India. 1 January 1970. Retrieved 6 March 2012. 